Freaky Facts

There are plenty of fact sheets about the Gateway Upgrade Project on its website.


Have you ever wanted to know more about how go viatag works? Visit school projects for more information.

Facts on the Gateway Bridge and the Gateway Upgrade Project

 

Gateway Bridge

Gateway Upgrade Project

Commenced

5 June 1980

9 March 2007

Opened

11 January 1986

under construction

Cost

Total project cost - $140 million
Bridge only - $92 million

Total project cost - $2.12 billion
Bridge only - $350 million (approx)

Owner

The Gateway Bridge Company Limited, now a subsidiary of Queensland Motorways Limited

Queensland Motorways Limited

Designer

Macdonald Wagner Pty Ltd in association with V.S.L. International of Switzerland

Maunsell Aecom and SMEC

Builder

Transfield (Qld) Pty Ltd

Leighton Abigroup Joint Venture

Length

1.63 kilometres

1.63 kilometres

Width

22 metres - six lane divided carriageway

27 metres - six lanes and a 4.5 metre shared pedestrian & cycle way with 4 viewing platforms

Height

64.5 metres above river level

64.5 metres above river level

Grade

5.27%

5.27%

Clearance

59.2 metres - river level to centre of main span

59.2 metres - river level to centre of main span

Shipping clearance

54 metres

54 metres

Main span

260 metres

260 metres

Concrete

150,000 tonnes

157,000 tonnes

Reinforced steel

9,900 tonnes

11,600 tonnes

Erection truss

650 tonnes

1,000 tonnes

Pre-stressing high tensile steel wire

2,500 tonnes; if the wire was stretched out it would join Cairns to Melbourne

 

Construction method

Main Span - Cast in-situ balanced cantilever Approaches - Pre-cast segmental span-by-span (joined with concrete stitch pour)

Main Span - Cast in-situ balanced cantilever Approaches - Match-casting segmental (joined with epoxy)


Facts on the Gateway Motorway and Gateway Extension
Length - 29 kilometres
Traffic counts - over 100,000 per day over the Bridge
Toll points

  • Murarrie
  • Kuraby

Facts on the Logan Motorway
Length - 32 kilometres
Traffic counts - over 90,000 per day.
Toll points

  • Heathwood
  • Loganlea
  • Paradise Road Interchange

Commenced

1 October 1987

Opened

31 December 1988

Cost

$77 million

Owner

The Logan Motorway Company Limited, now a subsidiary of Queensland Motorways Limited

Designer

Bornhorst and Ward Pty Ltd Gutteridge Haskins and Davey Pty Ltd

Macdonald Wagner Pty Ltd Rankine and Hill Pty Ltd

Builder

Crooks Mitchell Peacock Stewart (Qld) Pty Ltd

Length

32 kilometres

Width

Initially started as two lanes (single each way) then changed to 4 lanes (double each way) in 1997 and 2000

Financial advisor

Queensland Government Development Authority

Toll collection equipment provider

Toll Systems Technology Pty Ltd


Facts on the Paradise Road Interchange
The Paradise Road Interchange includes:

  • On and off-ramps from the Logan Motorway to Paradise Road
  • Signalised intersections from the ramps to Paradise Road
  • Toll plazas on the east bound on-ramp and west bound off-ramp
  • An extension of the existing Paradise Road overbridge by an additional 20 metres on the northern side of the Motorway
  • Construction of a new bridge under the interstate railway line
  • Drainage works, road marking and signage associated with the new road layout
  • Additional road lighting along the Logan Motorway and Paradise Road

Did you know?

  • The rail bridge over the Interchange was completed in 4 x 10 hour shut downs, saving three weeks on the construction program
  • Fast germinating native seeds, prevalent in the local area, were used for landscaping
  • More than 150,000 cubic metres of earth was moved to create the foundation for the on and off-ramps
  • All earth work materials were sourced from the site
  • Over 740 personnel worked on this project
  • Approximately 34,000 tonnes of asphalt was laid
  • 1800 metres of guardrail and 1600 metres of concrete barriers were erected
  • Reinforced concrete pipes were used instead of steel pipes, to ensure durability
  • Over 100 street lights were installed
  • The project was completed ahead of schedule